Edmond's 2nd Street Cones Clear in Stages, and the Sidewalk Crews Stay Longest

November 12, 2026

Heading east on Edmond Road from the west city limits, the orange barrels begin near Kelly Avenue and keep going. From Kelly to Fretz the right lane opens and closes as sidewalk crews move along. At Broadway, one direction of Edmond Road has been shut completely since mid-October. One block north, West Hurd Street near the BNSF tracks may be closed outright. East of I-35, between Saints Boulevard and Air Depot, the right lane of 2nd Street is fenced off for pipe big enough to stand in.

These are separate jobs, run by different departments, and each has its own end date. Very little of the work is repaving. Crews are laying water mains, adding electric capacity and rebuilding sidewalks. The closures that cause the biggest backups end soonest. The sidewalk project, which takes the least room, will be on the corridor the longest.

The Calendar, by End Date

Every date below comes from the City of Edmond or ODOT, and every one depends on the weather.

Project Where What's closed Scheduled to end
I-35 surface testing I-35 between 2nd St./US-77 and Waterloo Rd. One lane each way, 8 p.m. to 6 a.m. on weeknights Nov. 20, 2026
Edmond Road & Broadway intersection Edmond Road, Broadway to Fretz Westbound lanes, Phase 2 from Nov. 2 About two weeks after Nov. 2
MAIN-03 water lines 2nd St./US-66, Saints Blvd. to Air Depot Right lane, eastbound then westbound About three months from Sept. 24
Edmond Electric capacity work W. Hurd St. east of the BNSF tracks Possible full closure Jan. 20, 2027
Coffee Creek bridge replacement Westminster Road just north of SH-66 Full closure from Sept. 8 About six months, so roughly March 2027
ADA sidewalk and crosswalk project 2nd St./Edmond Road, Lexington Way to Sooner Rd. Right lanes as needed Into October 2027

Broadway and I-35 Clear First

The Edmond Road and Broadway project started Oct. 19. Crews are replacing concrete street panels, rehabilitating the traffic signals, and adding ADA and stormwater upgrades at one of downtown's busiest intersections. The city split the work into two phases of about two weeks each. During Phase 1, eastbound Edmond Road between Broadway and Fretz Avenue was closed, along with part of Broadway's southbound curb lane just north of the intersection. Phase 2 began early Monday, Nov. 2. Eastbound reopened and both westbound lanes closed, with "no westbound traffic" allowed for about two weeks, weather permitting. On that schedule the work should wrap up around mid-November. The city has said downtown stays open for business the whole time.

The interstate work has a fixed end date too. ODOT's Nov. 6 traffic advisory narrows northbound and southbound I-35 to one lane between US-77/SH-66/2nd Street and Waterloo Road from 8 p.m. to 6 a.m. on weeknights through Nov. 20, for surface testing. Late-evening drives home from Oklahoma City will feel it, and daytime commuters won't.

Both of these jobs block whole lanes, and both are scheduled to finish before Thanksgiving.

East of the Interstate, the Pipe Comes From Arcadia Lake

The right-lane closure on 2nd Street/US-66 between Saints Boulevard and Air Depot Boulevard is part of the MAIN-03 Water Infrastructure Project. The eastbound right lane closed Thursday, Sept. 24. A second phase moves the closure to the westbound right lane, and the city expects the two phases together to take about three months. On that estimate, the lane work on this stretch winds down around the end of the year.

What goes under that lane is the reason for the work. MAIN-03 installs a new 36-inch treated-water transmission line and a 48-inch raw-water line connecting the Arcadia Lake Water Treatment Plant with the I-35 and 2nd Street area. On the city's capital project map, the transmission-line work is listed at $53,576,197. It is funded by an Oklahoma Water Resources Board loan that will be repaid over 30 years through water use charges, and its anticipated completion is February 2027.

The pipe connects to a much larger project. The Oklahoma Water Resources Board describes the plant work as the third phase of an expansion of Edmond's Arcadia Lake plant, which was originally built in 1987. The expansion takes treatment capacity from 12 million gallons per day to 30 million. KOCO reported that the City Council approved a $377 million bid for the plant in June 2026. The lines on 2nd Street will carry that added capacity into town.

The water project also includes something for the trails. The city's project map says a new utility bridge across the Deep Fork will double as a pedestrian bridge for mountain bikers and walkers on the trails there. The latest update on that map has the piers in place and crews working on the abutments and slab foundations.

On Hurd Street, Wire for a Growing Downtown

One block north of the Broadway intersection, Edmond Electric began work near the BNSF tracks and West Hurd Street as early as Oct. 26. West Hurd east of the tracks may be completely closed until the anticipated completion date of Jan. 20, 2027, weather permitting. The city says the project will "increase electric system capacity and reliability and provide additional capacity to support continued development in Edmond's downtown area." Questions go to Edmond Electric at (405) 216-7660.

The council has recently approved development on this part of Hurd. At its Sept. 14 meeting, the City Council voted 5-0 to approve a development agreement with Hurd Courts, LLC, at North Santa Fe Drive and West Hurd Street. The project will include townhomes and retail, with an approximate completed value of $11 million. At the same meeting, the council voted 4-1 to approve a renovation of 19 Broadway, at the southwest corner of Broadway and Hurd. Plans call for retail and office space on floors two and three, a first-floor restaurant and a basement "speakeasy." That project's commencement deadline is Dec. 31, 2027. Hurd Courts has to start construction by June 30, 2027. The electric work is scheduled to finish well before either project has to break ground.

North of SH-66, a Bridge Takes Half a Year

One closure is away from the 2nd Street corridor but on the same calendar. News 9 reported that Westminster Road just north of SH-66 closed for about six months beginning Tuesday, Sept. 8, so the bridge over Coffee Creek can be replaced. Counting six months from that start date, the road is due to reopen around March 2027. Drivers on the east side who use Westminster to reach SH-66 will need a detour through the winter.

The Sidewalk Project Outlasts Them All

The project that looks smallest will stay the longest. The sidewalk and accessibility project covers about six miles of 2nd Street/Edmond Road, from S. Lexington Way at the west city limits to Sooner Road. Crews are building new sidewalk, repairing existing sidewalk, relocating signs, fixing curb and gutter, installing ramps with tactile warning pads, and improving crosswalks. ODOT administers the project in partnership with the City of Edmond. The city's project map says the goal is to fill gaps in the corridor's sidewalk, bring existing walks and ramps up to ADA standards, and restripe crosswalks so drivers can see them better. The project map lists the cost at $4,349,918.99, supported by an ODOT grant of $2,142,400.

Progress has been steady and slow. Lane closures started Tuesday, May 26, 2026, on the west end. The first 1.5 miles, from Lexington Way to Kelly Avenue, are finished. On Oct. 27 the work moved to Kelly through Fretz, with eastbound and westbound right lanes closing as needed. That segment runs straight into the Broadway intersection, so for a few weeks this fall the two projects overlapped on the same blocks of downtown Edmond Road. After Fretz, the crews still have to work east past I-35 to Sooner Road. The city expects the job to continue into October 2027, weather permitting.

Because the work moves block by block, it closes the right lane only where crews are working that day. That makes it easier to drive past than a full closure and keeps it on the road far longer. The westbound Broadway closure should be gone before Thanksgiving, the pipe work on 2nd Street east of I-35 around the new year, and the Hurd Street closure by Jan. 20. Barrels for the sidewalk project will keep showing up somewhere between Kelly Avenue and Sooner Road through next fall.

If you're thinking about selling a home near the corridor, or buying one, and want to talk through how a long construction season along a main road can affect showings and access, Matt Berry can walk you through it. Schedule a consultation and bring your questions about specific streets.

Let’s Find Your Next Home

Whether you’re buying, selling, or planning your next move, Matt Berry is ready to work for you. Reach out today to start your real estate journey with confidence and clarity.